Scaffolding removal plan and requirements

  1. Before dismantling the outer frame, the person in charge of the unit engineering shall convene relevant personnel to conduct a comprehensive inspection and visa confirmation of the frame project. When the building construction is completed and it is not needed, the scaffolding can be removed.

2.Scaffolds should be dismantled with warning signs placed on them to prevent non-operators from passing and ground construction personnel to be able to do it.

3.The removal of long vertical poles and inclined poles should be carried out by two people. It is not suitable to work alone. Check whether it is firm when you are off work. If necessary, temporary fixing support should be added to prevent accidents.

4.Before removing the outer frame, please remove the debris left in the opening of the aisle and remove it in the order of installation.

5.In case of strong wind, rain, snow, etc., the outer frame cannot be removed.

6.Dismantled steel pipes and fasteners should be stacked and classified. Throwing at high altitude is strictly prohibited.

7.When the suspended steel pipes and fasteners are transported to the ground, they should be stacked in a timely manner according to the variety specifications.