Scaffolding pole foundation

(1) The height of floor-standing scaffolding should not exceed 35m. When the height is between 35 and 50m, unloading measures must be taken. When the height is greater than 50m, unloading measures must be taken and special plans must be taken.

Make expert arguments.

(2) The scaffolding foundation shall be flat, tamped and concrete hardened. The foundation shall be hardened with 100mm thick C25 concrete, and the base or pad shall be set at the bottom of the pole. The backing plate should be of different lengths

Wooden backing boards with less than 2 spans, thickness not less than 50mm, and width not less than 200mm.

(3) Vertical and horizontal sweeping poles must be set for floor-standing scaffolding, and the vertical sweeping pole should be fixed on the vertical pole immediately below the vertical sweeping pole with direct fasteners. When the vertical pole foundation is not at the same height, the vertical sweeping pole in the high place must be extended to the lower place by two spans and fixed with the pole.

(4) Drainage measures should be taken into account for the scaffolding foundation. The elevation of the bottom surface of the scaffolding base should be 50mm higher than the outdoor natural floor, and the outer side of the pole foundation should be set with a drainage ditch with a cross-section of no less than 200mm × 200mm to ensure that the scaffolding foundation does not accumulate water.


Post time: Aug-09-2022


We use cookies to offer a better browsing experience, analyze site traffic, and personalize content. By using this site, you agree to our use of cookies.

Accept