Scaffolding engineering safety production standardization

1. The erection of scaffolding should meet the requirements of the standard specifications. A 200mm wide warning tape should be installed every 3 floors or 10m, fixed on the outside of the pole, and the scissors should be continuously installed.
2. Color: Paint the surface of the steel pipe of the scaffold, paint the surface of the scissors support and the warning tape, and hang the green dense safety net on the inside of the scaffold. The safety net is tightly closed and tensioned. No damage, the color is new and bright.

 

1. The foundation of the floor-standing external scaffold should be flattened and compacted. On the basis, a backing plate is set along the length direction of the outer scaffold. The material of the backing plate can be wooden scaffolding or channel steel backing.
2. Set the vertical and horizontal sweeping poles at 200mm below the pole, the vertical sweeping poles are on the top, and the horizontal sweeping poles are on the bottom, both of which are connected to the poles.
3. Set drainage ditches around the scaffold and adopt organized drainage.
4. When the foundation of the scaffolding pole is not at the same height, the vertical sweeping pole at the high place must be extended to the lower place by two spans and fixed with the pole. The height difference is not more than 1m. Less than 500mm.


Post time: Mar-17-2023


We use cookies to offer a better browsing experience, analyze site traffic, and personalize content. By using this site, you agree to our use of cookies.

Accept