First, preparation before construction of steel pipe scaffolding
(1) Site survey: Before the construction of scaffolding, a detailed survey of the construction site should be conducted to understand factors such as topography, geology, and climate conditions in order to reasonably plan the construction plan of the scaffolding.
(2) Planning and design: According to the survey results and combined with construction requirements, a scaffolding construction plan is formulated, including parameters such as height, span, and load to ensure that the construction requirements are met.
(3) Approval and filing: Submit the construction plan to the relevant departments for approval, obtain a construction permit, and ensure construction compliance.
Second, material inspection and selection
(1) Steel pipe inspection: Check the specifications, wall thickness, length, and other parameters of the steel pipe to ensure that it meets the national standards and construction plan requirements. Steel pipes with defects such as rust, deformation, and cracks should be replaced in a timely manner.
(2) Fastener inspection: Check the model, material, strength, and other parameters of the fastener to ensure that it matches the steel pipe and can meet the construction load requirements. Fasteners should be intact and free of defects such as cracks and deformation.
(3) Inspection of materials such as safety nets and scaffolding boards: Check the material, size, strength, and other parameters of safety nets and scaffolding boards to ensure that they meet the requirements of the construction plan. The materials should not be damaged or aged.
Third, technical personnel training and organization
(1) Technical personnel training: Train technical personnel involved in scaffolding construction to familiarize them with the construction plan, master construction techniques, and understand safe operating procedures.
(2) Operator training: Provide safety education and operation skills training to operators to improve their safety awareness and operation skills.
(3) Construction organization: Clarify the responsibilities of managers and operators at all levels, formulate construction plans and schedules, and ensure that construction is carried out in an orderly manner. At the same time, a safety inspection team should be set up to supervise and inspect the construction and use of scaffolding to ensure construction safety.
Fourth, supervision during the scaffolding construction process
(1) Supervisor training: Ensure that all supervisors have received professional training, are familiar with the scaffolding construction procedures and safety standards, and are able to discover and correct problems during the construction process.
(2) Construction process records: Keep detailed records of the scaffolding construction process, including construction time, construction personnel, materials used, etc., to facilitate subsequent review and tracking.
(3) Strictly follow the specifications for construction: Supervisors must ensure that all construction personnel strictly abide by the scaffolding construction specifications and prohibit any illegal operations.
Fifth, scaffolding safety facilities
(1) Anti-fall facilities: Set up anti-fall facilities around the working surface of the scaffolding, such as safety nets
or anti-fall platforms to prevent people or materials from falling from high altitudes.
(2) Anti-slip treatment of scaffolding: Perform anti-slip treatment on the walking surface of the scaffolding, such as laying anti-slip mats,
to prevent people from slipping in bad weather or when the scaffolding is wet.
(3) Appropriate lighting and ventilation: Ensure that there are appropriate lighting facilities and ventilation equipment inside the scaffolding to ensure safety when working in dim or harsh environments.
Sixth, regular inspection and maintenance of scaffolding
(1) Regular structural integrity inspection: Regularly inspect the structural integrity of the scaffolding, including the connection of steel pipes, the stability of the supporting structure, etc., to ensure that the scaffolding can safely bear the load.
(2) Timely treatment of damage: Once any damage or wear is found on the scaffolding, it should be stopped and repaired immediately. It is prohibited to continue working on the damaged scaffolding.
(3) Equipment update and replacement: For equipment that is seriously aged or frequently has problems, it should be updated or replaced in a timely manner to ensure that the scaffolding is always in good working condition.
Seventh, precautions during the use of scaffolding
1. Limit the use load
(1) Strictly control the load: When using steel pipe scaffolding, the load must be strictly controlled to ensure that the load does not exceed the limit specified in the design.
(2) Evenly distribute the load: When placing materials, tools, and other items on the scaffold, they should be evenly distributed to avoid excessive local loads.
(3) Prevent overloading: During use, the deformation and settlement of the scaffold should be checked regularly to detect and prevent overloading in a timely manner.
Eighth, regulations on personnel passage
(1) Set up safe passages: Set up safe passages at appropriate locations on the scaffold to ensure safe passage of personnel.
(2) Use protective facilities: When personnel pass on the scaffold, they should use protective facilities such as safety belts and safety nets.
(3) Prohibit running and jumping: When personnel passes on the scaffold, running, jumping and other behaviors are prohibited to avoid accidents.
Ninth, measures to deal with severe weather.
(1) Stop using: When encountering severe weather such as strong winds, rain, and snow, the scaffold should be stopped immediately.
(2) Reinforcement measures: Before the onset of severe weather, reinforcement measures should be taken, such as adding diagonal braces and reinforcing vertical poles, to ensure the stability of the scaffolding.
(3) Drainage measures: In rainy and snowy weather, drainage measures should be taken to prevent water accumulation on the scaffolding, thereby avoiding rust and deformation.